Information.

Length overall 94.41 m
Beam moulded 30.00 m
Depth moulded 6.10 m

The barge was docked on 12 of January and undocked on 8th of march.

Work Description.

  1. Blasting and painting of the hull. 4,100 sqm was blasted and painted with four coats of paint.
  2. We overhauled of outboard valves – 28 pcs.
  3. Renewal of sacrificial Anodes – 96 pcs.
  4. Eight sheave units on the four corners of the barge has been removed to the workshop, blasted and disassembled. Four pieces were modified and installed on the barge.
  5. We have changed the name of the vessel – new letters were cut on the plasma cutting machine and welded. New name – Prabha.
  6. We have fitted new strainers and two valves for the sea chests.
  7. Aur mechanical team work together with the crew for engine repairs.
  8. We also made some steel renewals and railing repairs.

We have completed all the works and the barge left the shipyard.

Impressions.

20240112 071422
20240112 080348
20240112 082654
20240112 173213
20240115 082735
20240117 093150
20240117 142330
20240122 150013
20240122 150320
20240122 151105
20240123 100142
20240127 101928
20240301 151330
20240301 151425
20240110 125747

back

To top